Roadwork Updates

City Sanitary Sewer Work
Phase 3
May 27- June 23

Phase 2 of the City of Bellevue utility work is finishing and the crews are getting ready to start Phase 3, May 27th. 

Phase 3:
May 27th to June 23rd (no work will take place May 24th - 26th in observance of the Memorial Day holiday).

Drivers will encounter lane closures on NE 4th Street between 106th Avenue and Bellevue Way.

Work hours will take place between 7:00 am and 3:30 pm.

City Sanitary Sewer Work </br> Phase 3 </br> May 27- June 23

City Sanitary Sewer Work
Phase 2
May 12 - 23

Phase 1 of the City of Bellevue roadwork is wrapping up and we are getting ready to start Phase 2, May 12th. Below is the outline of Phase 2:

Phase 2:
May 12th through Approximately May 23rd

Drivers will encounter full lane closures in both directions on Bellevue Way, from NE 6th Street to NE 4th Street.

Work hours will take place between 7:00 am and 9:00 pm (Full lane closures will remain in place 24/7 during this phase.)

We will distribute additional information as it becomes available.

City Sanitary Sewer Work </br> Phase 2 </br> May 12 - 23
Sign up here for email updates on Construction and Roadwork associated with the Lincoln Square Expansion and Bellevue Square Expansion projects.